A1 Complete Builders works close with various architects and engineers and this is another project for J.L.A Consulting Engineers whom we have worked on various projects with Pont Quay, Fowey etc.
This particular party wall collapsed in the winter storms December 2012 and A1 started July 2013 once given the go ahead by J.L.A.
All collapsed soil and stone was removed and separated, stone cleaned off and stored ready to re-use plus 10%.
The new construction was a standard 7 Newton blocks Built on the flat starting @ 1.5 meter wide part way up decreasing in size as it was constructed.
Once constructed it was then rebuilt in stone. [Stone Faced] to match existing.
Duration of time on site: 8 weeks